A 14-mile stretch of a highway in Carroll County soon will have a new, smoother surface.
According to MoDOT, it contracted with Capital Paving and Construction, LLC, to resurface Highway 10, from Route FF southwest of Norborne to U.S. Business Route 65 in Carrollton.
The contractor is scheduled to begin work Wednesday, October 10, after facing delay. The project is expected to be completed by mid-November.
In addition to resurfacing, there will be shoulder, guardrail and erosion-control phases of the project, and traffic will be reduced to one lane in two-mile segments with flaggers and pilot cars directing motorists through the work zone, which may move daily. Crews will work daylight hours Monday through Saturday for the duration of the project. But there also is the possibility of some Sunday work, if the contractor feels it necessary to complete the project on schedule.
All scheduled roadwork is weather permitting and subject to change.