Work on a resurfacing and shoulder-improvement project on U.S. Highway 24 has been suspended.
The Missouri Department of Transportation says it has contracted with Capital Paving and Construction to complete the resurfacing and shoulder improvements on U.S. Highway 24- from approximately two miles west of Highway 41 near DeWitt to Highway 5 in Keytesville.
The contractor has completed some preliminary off-road work, but roadway resurfacing is now scheduled to begin after the Memorial Day holiday.
A pilot car and flaggers will direct motorists around the lane closures. A 12-foot width restriction will be in place for the duration of the project.
During daylight hours, Monday through Friday, crews will be on-site, and the work zone will be active. If necessary, some work may occur on Saturdays to complete the project on schedule. All work is expected to be complete by the end of July 2020.
All work is weather permitting, and schedules are subject to change.
For more information, call (888) ASK-MODOT (275-6636).