The Marshall Municipal Utilities Board of Public Works considered several bids for the purchase of a new walk-behind concrete saw during its meeting on Thursday, December 29.
The board opened bids on December 21, and two bids were received from one vendor. Both bids came under the $35,000 budget. Underground Facilities Director Grant Piper recommended the board accept the bid from Logan Contractors Supply for a 2023 Husqvarna FS 5000D T4.
The cost of the bid is $33,780. Delivery time is ten months from the order date. The board accepted the bid.
In other news from the meeting, the board passed a motion to approve Burns and McDonnell to renew MMU’s current Owners Supervised Water Distribution Plan. The last plan was done in 2018 bu McClure Engineering.