The Marshall Municipal Utilities Board of Public Works approved several action items during its meeting on Thursday, February 15.
The board started by approving a motion to request bids to supply and install doors, frames, and all necessary hardware on the original water treatment plant building.
The board then considered a motion to conduct well treatment and maintenance. MMU wants to treat five wells and pull two well pumps for inspections and repair. The board approved a motion to request proposals for the project.
Also, the board approved a motion to request proposals for the Southeast Substation T1 re-gasket and maintenance. The substation transformer was put in service in 1976. The total budget for the work is $180,000.