A resurfacing project is set to begin next week on several routes in Howard and Randolph counties.

Construction crews working with the Missouri Department of Transportation plan to begin setting signs along the first routes this week, with resurfacing scheduled to begin Monday, March 17.
The current planned schedule of work includes:
-Howard County Route EE from Route A to Route J: March 17 – 21.
-Howard County Route A from Route B to Route 124: March 17 – 31.
-Boone/Randolph County Route T from Route B to Route F: March 17 – 24.
-Howard County Route AA from Route 87 to Route E: March 26 – April 1.

During construction, each roadway may be reduced to one lane between 7 a.m. and 7 p.m., with flaggers and a pilot car guiding motorists through the work zone. All work is weather-dependent, and schedules are subject to change.